62 completion rate for Jerash Governorate Councils capital projects in 2025

Khaberni - The completion rate for capital projects that were implemented from the governorate council's allocations last year was 62%, with a total of 229 projects distributed across 20 sectors.

The Governor of Jerash, Malek Khraysat, told "Al-Mamlaka" that the total completion rate reached 62%, distributed across 20 sectors. The completion rate in the Directorate of Education was 33% with a total of 20 projects, while the Public Works sector recorded a completion rate of 91% with a total of 23 projects.

Khraysat added that the completion rate in the water sector projects was 2% distributed over 30 projects, the health sector 70% with a total of 15 projects, the agriculture sector 100% with a total of 8 projects, the social development sector 97% with a total of 7 projects, and the tourism sector 11% with a total of 3 projects.

He indicated that the completion rate in the projects of the archeology sector was 13% distributed over two projects, and in the youth sector 31% distributed over 13 projects, while the completion rate in the Waqf sector was 99% distributed over 17 projects.

Khraysat pointed out that the completion rate in a number of projects reached 100%, distributed over 6 projects, whereas the completion rate in the Jerash Cooperative Directorate was 0% in one project, the environment sector 55% in one project, and the vocational training sector 100% in one project.

He clarified that the completion rate in the Palestinian affairs amounted to 100% distributed over two projects, and in the projects of the National Company for Employment and Training 100% for one project, the internal sector 97% distributed over 4 projects, and the higher education sector 95% for one project.

The completion rate in the projects of the local administration sector also reached 49% distributed over 73 projects, according to the Governor of Jerash, Malek Khraysat.